INSTALLMENT OF YST PUMP HOUSE UPDATE

Time to read
less than
1 minute
Read so far

INSTALLMENT OF YST PUMP HOUSE UPDATE

By
Alyssa Mathis

According to Menning Excavating Inc., of Mitchell who are currently working on the installation of the new pump house southeast of Lake Andes, there is currently a delay in construction. Work on the project has halted as the company waits to hear back from the Yankton Sioux Tribe on a change that needs to happen with the voltage panel. The current voltage control panel that the company is supposed to install is not the correct voltage as it does not match the voltage of the existing panel that was placed by Northwestern Energy. There is no foreseeable completion date. The date will all depend on the decision made about the panel and the potential winter weather.